Grid

Projects

Projects

Where is Chapel Farm up to?

Each status below comes from a named source and date.

Battery · England, Eastern

Planning

Planning
Granted
18 Jan 2019
DESNZ REPD, 3 Aug 2026
Construction
Built
1 Mar 2022
DESNZ REPD, 3 Aug 2026
Operational status
Operational
1 May 2023
DESNZ REPD, 3 Aug 2026

Connection

Connection
Battery project, epj_e38cf449f7361b6a

Measures

Rated power
49.5 MW
Connection capacity
Not published
Storage energy
Not published