Projects
Where is Leamington Road, Princethorpe - Ash Tree Solar Photovoltaic Arrays up to?
Each status below comes from a named source and date.
Solar PV · England, West Midlands
Planning
- Planning
- Granted
- 6 Aug 2025
- DESNZ REPD, 3 Aug 2026
- Construction
- Not started
- DESNZ REPD, 3 Aug 2026
- Operational status
- Proposed
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Solar PV project, epj_e509d3aa931c7b67
Measures
- Rated power
- 16.8 MW
- Connection capacity
- Not published
- Storage energy
- Not published