Where is New Lodge Farm - ACT up to?
Each status below comes from a named source and date.
Advanced conversion · Wales
Planning
- Planning
- Refused
- 5 Feb 2016
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Advanced conversion project, epj_e5a7b4947a05c27a
Measures
- Rated power
- 12.0 MW
- Connection capacity
- Not published
- Storage energy
- Not published