Projects
Where is Watts Group Factory Site up to?
Each status below comes from a named source and date.
Battery · England, South West
Planning
- Planning
- Abandoned
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Battery project, epj_e89707a9c16a7092
Measures
- Rated power
- 10.0 MW
- Connection capacity
- Not published
- Storage energy
- Not published