Grid

Projects

Projects

Where is Gibraltar Road - Solar photovoltaic system up to?

Each status below comes from a named source and date.

Solar PV · England, Yorkshire and Humber

Planning

Planning
Granted
19 Jan 2024
DESNZ REPD, 3 Aug 2026
Construction
Not started
DESNZ REPD, 3 Aug 2026
Operational status
Proposed
DESNZ REPD, 3 Aug 2026

Connection

Connection
Solar PV project, epj_e8d6a2bbca8c0046

Measures

Rated power
0.4 MW
Connection capacity
Not published
Storage energy
Not published