Projects
Where is North Wiltshire Biomass Power Plant up to?
Each status below comes from a named source and date.
Biomass · England, South West
Planning
- Planning
- Refused
- 11 Sep 2001
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Biomass project, epj_ea1d432e9d752762
Measures
- Rated power
- 5.5 MW
- Connection capacity
- Not published
- Storage energy
- Not published