Grid

Projects

Projects

Where is S P & G Blything, Cross Lanes - Biomass Boiler up to?

Each status below comes from a named source and date.

Biomass · England, North West

Planning

Planning
Granted
22 Nov 2022
DESNZ REPD, 3 Aug 2026
Construction
Built
DESNZ REPD, 3 Aug 2026
Operational status
Operational
1 Jan 2023
DESNZ REPD, 3 Aug 2026

Connection

Connection
Biomass project, epj_ea74613d362794e4

Measures

Rated power
0.3 MW
Connection capacity
Not published
Storage energy
Not published