Biomass · England, East Midlands
Planning
- Planning
- Granted
- 6 Jun 2023
- DESNZ REPD, 3 Aug 2026
- Construction
- Under construction
- 1 Feb 2023
- DESNZ REPD, 3 Aug 2026
- Operational status
- Proposed
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Biomass project, epj_ec9202f7274aa476
Measures
- Rated power
- 1.6 MW
- Connection capacity
- Not published
- Storage energy
- Not published