Where is Pearie Law 2 - Wind turbines up to?

Each status below comes from a named source and date.

Onshore wind · Scotland

Planning

Planning
Granted
22 Dec 2021
DESNZ REPD, 3 Aug 2026
Construction
Not started
DESNZ REPD, 3 Aug 2026
Operational status
Proposed
DESNZ REPD, 3 Aug 2026

Connection

Connection
Onshore wind project, epj_eca9060caa8af7bb

Measures

Rated power
14.4 MW
Connection capacity
Not published
Storage energy
Not published