Projects
Where is Admiralty Road - Battery Energy Storage Facility up to?
Each status below comes from a named source and date.
Battery · England, Eastern
Planning
- Planning
- Revised
- 3 Aug 2021
- DESNZ REPD, 3 Aug 2026
- Operational status
- Proposed
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Battery project, epj_ed0f66793cbe0fbf
Measures
- Rated power
- 49.9 MW
- Connection capacity
- Not published
- Storage energy
- Not published