Where is Land Parcel North of Goddards up to?
Each status below comes from a named source and date.
Solar PV · England, South East
Planning
- Planning
- Granted
- 7 Aug 2015
- DESNZ REPD, 3 Aug 2026
- Construction
- Built
- 5 Feb 2016
- DESNZ REPD, 3 Aug 2026
- Operational status
- Operational
- 30 Mar 2016
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Solar PV project, epj_ef4d2f4eb4dcea6b
Measures
- Rated power
- 5.0 MW
- Connection capacity
- Not published
- Storage energy
- Not published