Grid

Projects

Projects

Where is Glebe Horsford - Solar Farm up to?

Each status below comes from a named source and date.

Solar PV · England, Eastern

Planning

Planning
Granted
1 Jul 2025
DESNZ REPD, 3 Aug 2026
Construction
Not started
DESNZ REPD, 3 Aug 2026
Operational status
Proposed
DESNZ REPD, 3 Aug 2026

Connection

Connection
Solar PV project, epj_ef9635b3a96024ae

Measures

Rated power
18.0 MW
Connection capacity
Not published
Storage energy
Not published