Solar PV · England, East Midlands
Planning
- Planning
- Granted
- 17 Aug 2015
- DESNZ REPD, 3 Aug 2026
- Construction
- Built
- 19 Oct 2015
- DESNZ REPD, 3 Aug 2026
- Operational status
- Operational
- 21 Dec 2015
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Solar PV project, epj_efa00a5c0d1c4959
Measures
- Rated power
- 3.5 MW
- Connection capacity
- Not published
- Storage energy
- Not published