Onshore wind · England, East Midlands
Planning
- Planning
- Granted
- 6 Jul 2012
- DESNZ REPD, 3 Aug 2026
- Construction
- Built
- 18 Feb 2014
- DESNZ REPD, 3 Aug 2026
- Operational status
- Operational
- 15 Dec 2014
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Onshore wind project, epj_eff2d4cbf140b776
Measures
- Rated power
- 10.0 MW
- Connection capacity
- Not published
- Storage energy
- Not published