Projects
Where is Strathruddie, Kinglassie - Solar farm up to?
Each status below comes from a named source and date.
Battery · Scotland
Planning
- Planning
- Granted
- 16 Mar 2022
- DESNZ REPD, 3 Aug 2026
- Construction
- Not started
- DESNZ REPD, 3 Aug 2026
- Operational status
- Proposed
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Battery project, epj_f0e4f9e54d2f4b7f
Measures
- Rated power
- 20.0 MW
- Connection capacity
- Not published
- Storage energy
- Not published