Where is Blyth Offshore Wind Test Site up to?

Each status below comes from a named source and date.

Offshore wind · England, Offshore

Planning

Planning
Granted
8 Nov 2013
DESNZ REPD, 3 Aug 2026
Construction
Built
22 Oct 2016
DESNZ REPD, 3 Aug 2026
Operational status
Operational
22 Oct 2017
DESNZ REPD, 3 Aug 2026

Connection

Connection
Offshore wind project, epj_f0fd3eb4c72ebd2f

Measures

Rated power
41.5 MW
Connection capacity
Not published
Storage energy
Not published