Where is Pond Industrial Park, Whitburn Road - Pond Battery Storage up to?

Each status below comes from a named source and date.

Battery · Scotland

Planning

Planning
Granted
24 Mar 2025
DESNZ REPD, 3 Aug 2026
Construction
Not started
DESNZ REPD, 3 Aug 2026
Operational status
Proposed
DESNZ REPD, 3 Aug 2026

Connection

Connection
Battery project, epj_f4b7cc0e810b4489

Measures

Rated power
200.0 MW
Connection capacity
Not published
Storage energy
Not published