Solar PV · England, South East
Planning
- Planning
- Granted
- 7 Oct 2011
- DESNZ REPD, 3 Aug 2026
- Construction
- Built
- DESNZ REPD, 3 Aug 2026
- Operational status
- Operational
- 28 Feb 2013
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Solar PV project, epj_f565945db0a3db66
Measures
- Rated power
- 5.0 MW
- Connection capacity
- Not published
- Storage energy
- Not published