Solar PV · Wales

Planning

Planning
Application submitted
30 Dec 2025
DESNZ REPD, 3 Aug 2026
Operational status
Proposed
DESNZ REPD, 3 Aug 2026

Connection

Connection
Solar PV project, epj_f625289b2e13704e

Measures

Rated power
30.0 MW
Connection capacity
Not published
Storage energy
Not published