Where is Sunnyside wind cluster up to?

Each status below comes from a named source and date.

Onshore wind · Scotland

Planning

Planning
Granted
19 Dec 2013
DESNZ REPD, 3 Aug 2026
Construction
Built
15 Jun 2015
DESNZ REPD, 3 Aug 2026
Operational status
Operational
15 Nov 2015
DESNZ REPD, 3 Aug 2026

Connection

Connection
Onshore wind project, epj_f69daff203382e5f

Measures

Rated power
1.0 MW
Connection capacity
Not published
Storage energy
Not published