Where is Wednesbury up to?
Each status below comes from a named source and date.
Energy from waste · England, West Midlands
Planning
- Planning
- Granted
- 25 Mar 2015
- DESNZ REPD, 3 Aug 2026
- Construction
- Under construction
- 26 Apr 2017
- DESNZ REPD, 3 Aug 2026
- Operational status
- Proposed
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Energy from waste project, epj_f72336041a8150e2
Measures
- Rated power
- 2.0 MW
- Connection capacity
- Not published
- Storage energy
- Not published