Where is Pierces Farm up to?
Each status below comes from a named source and date.
Solar PV · England, South East
Planning
- Planning
- Granted
- 19 Mar 2014
- DESNZ REPD, 3 Aug 2026
- Construction
- Built
- 16 Oct 2014
- DESNZ REPD, 3 Aug 2026
- Operational status
- Operational
- 15 Mar 2015
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Solar PV project, epj_f8eb53f89ed19e90
Measures
- Rated power
- 1.7 MW
- Connection capacity
- Not published
- Storage energy
- Not published