Advanced conversion · England, East Midlands
Planning
- Planning
- Granted
- 7 Sep 2010
- DESNZ REPD, 3 Aug 2026
- Construction
- Built
- 4 Apr 2016
- DESNZ REPD, 3 Aug 2026
- Operational status
- Operational
- 15 Mar 2018
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Advanced conversion project, epj_f976c5677b03a0f9
Measures
- Rated power
- 10.5 MW
- Connection capacity
- Not published
- Storage energy
- Not published