Where is River Lochy Hydro up to?
Each status below comes from a named source and date.
Hydro · Scotland
Planning
- Planning
- Granted
- 19 Dec 2013
- DESNZ REPD, 3 Aug 2026
- Construction
- Built
- 13 Mar 2015
- DESNZ REPD, 3 Aug 2026
- Operational status
- Operational
- 16 Aug 2016
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Hydro project, epj_f9ed4973d1e7a9d3
Measures
- Rated power
- 2.0 MW
- Connection capacity
- Not published
- Storage energy
- Not published