Solar PV · England, East Midlands

Planning

Planning
Granted
11 Feb 2015
DESNZ REPD, 3 Aug 2026
Construction
Built
16 Dec 2015
DESNZ REPD, 3 Aug 2026
Operational status
Operational
16 Feb 2016
DESNZ REPD, 3 Aug 2026

Connection

Connection
Solar PV project, epj_f9f50473a9166616

Measures

Rated power
6.1 MW
Connection capacity
Not published
Storage energy
Not published