Solar PV · England, Yorkshire and Humber

Planning

Planning
Granted
14 Sep 2015
DESNZ REPD, 3 Aug 2026
Construction
Built
15 Jan 2016
DESNZ REPD, 3 Aug 2026
Operational status
Operational
27 Mar 2016
DESNZ REPD, 3 Aug 2026

Connection

Connection
Solar PV project, epj_faf21e11847a2082

Measures

Rated power
5.0 MW
Connection capacity
Not published
Storage energy
Not published