Projects
Where is Burnfoot East Wind Farm (further extension) up to?
Each status below comes from a named source and date.
Onshore wind · Scotland
Planning
- Planning
- Granted
- 27 Mar 2019
- DESNZ REPD, 3 Aug 2026
- Construction
- Built
- 1 Sep 2019
- DESNZ REPD, 3 Aug 2026
- Operational status
- Operational
- 1 Jul 2020
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Onshore wind project, epj_fbbc081fbc6d3c91
Measures
- Rated power
- 10.8 MW
- Connection capacity
- Not published
- Storage energy
- Not published