Where is Bunkers Hill Farm - Solar farm & Battery stations up to?

Each status below comes from a named source and date.

Solar PV · England, South East

Planning

Planning
Granted
11 Nov 2021
DESNZ REPD, 3 Aug 2026
Construction
Under construction
15 May 2023
DESNZ REPD, 3 Aug 2026
Operational status
Proposed
DESNZ REPD, 3 Aug 2026

Connection

Connection
Solar PV project, epj_fc47353b4fbf8b8f

Measures

Rated power
49.9 MW
Connection capacity
Not published
Storage energy
Not published