Onshore wind · Scotland
Planning
- Planning
- Granted
- 14 Sep 2007
- DESNZ REPD, 3 Aug 2026
- Construction
- Built
- 1 Apr 2009
- DESNZ REPD, 3 Aug 2026
- Operational status
- Operational
- 11 Oct 2010
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Onshore wind project, epj_fde2d8a3b846efc1
Measures
- Rated power
- 38.0 MW
- Connection capacity
- Not published
- Storage energy
- Not published