Where is Bluestone Farm, Low Lands - Solar Farm up to?

Each status below comes from a named source and date.

Solar PV · England, North East

Planning

Planning
Granted
28 May 2024
DESNZ REPD, 3 Aug 2026
Construction
Not started
DESNZ REPD, 3 Aug 2026
Operational status
Proposed
DESNZ REPD, 3 Aug 2026

Connection

Connection
Solar PV project, epj_fe3b2800b4a95083

Measures

Rated power
50.0 MW
Connection capacity
Not published
Storage energy
Not published