Where is Lower Melville Wood up to?

Each status below comes from a named source and date.

Landfill gas · Scotland

Planning

Planning
Granted
DESNZ REPD, 3 Aug 2026
Construction
Built
DESNZ REPD, 3 Aug 2026
Operational status
Operational
28 Feb 2007
DESNZ REPD, 3 Aug 2026

Connection

Connection
Landfill gas project, epj_fedd84d25b7b8c43

Measures

Rated power
1.0 MW
Connection capacity
Not published
Storage energy
Not published